We hope to use this facility as a hub to engage the Muslim community in Milton, Oakville and Burlington. We are especially excited about engaging the children of the growing Muslim community through all kinds of event including sports, mentoring, community service game nights etc.

MAM Board continues to pursue the organization’s main objective of establishing a place of worship. The 4269 Regional Road property acquired for this purpose is currently undergoing reconstruction.


Milestones Achieved 

√ 12 Acres paid off property

√ Zoning approved as place of worship

√ Site plan approved for Civil work dated July 31, 2018

√ Hired contractor for Civil work dated Sep 05, 2018

√ Construction of Civil work inShaa Allah start 2nd or 3rd week of September 2018.

√ Expected date for completion of civil work is November 30, 2018.


Project Status

The construction work is broken down into three phases.

Phase 1  

Site Plan Approval

Completed

• Prepare Site for construction
• Slit Fencing
• Tree hoarding
• Left Turn Signal
• Letter of credit
• Site Plan agreement
• Revised Grading Plan
… approximate $335,150

Pictures of Phase 1

http://miltonmasjid.com/hicc-construction-pictures

Phase 2

Civil Work

In Progress

• Fire Tanks
• Septic Tank
• Parking Lot and Gravel driveway
• Landscaping, Etc
.… approximate $357,515
Phase 3

Building Renovation and Construction

In Progress

• Fire safety additions
• Reinforce floors
• Mechanical, Electrical, Heating
• Prayer area, Bathroom, wudu area, Etc
.… approximate $603,000

 


Project Phases and Cost Estimate


Proposed Floor Plan

√ Hired Architect dated October, 2017

√ Created draft floor plan dated January, 2018

√ Draft floor plan approved by BOD and members dated February, 2018.

√ Architect attended meeting with city planner about the draft floor plan and received input from city planner dated March, 2018

√ Architect created base drawing for pre consultant meeting with city, region and conservation officials dated August, 2018

√ Meeting is hopefully schedule in next couple of week. Meeting request already sent dated August, 2018


Funding Targets

Project financial status
Project cost 1,300,000
Total Funds Raised (Incl. QH) 1,160,000
Available Funds 850,000
Funds Spent on project 310,000
Qard-e-Hasan 258,000
Funds required 398,000

Donate Now

To complete this project successfully and on time, we need your financial support and prayers brothers and sisters. Please donate generously to have this place ready and open for us as soon as possible.

You can make a one time or recurring donation using the following methods

  • Credit Card, Paypal
  • Check
    • Please make the check out to the “Muslim Association of Milton”
    • You can mail the check to the address below, or drop it at the donation boxes at Juma, etc.
  • Direct Transfer
    • TD Canada Trust Bank
    • Transit # 3058, Account # 5000909

Location of the Project

HICC Address

4269 Regional Rd 25,

Oakville, ON L6M 4E9

“Whoever builds a mosque for Allah, then Allah will build for him a house like it in Paradise.”

Source: Ṣaḥīḥ al-Bukhārī 439, Ṣaḥīḥ Muslim 533