Masjid Project

Halton Islamic Community Center

(HICC)


Project Overview

We hope to use this facility as a hub to engage the Muslim community in Milton, Oakville and Burlington. We are especially excited about engaging the children of the growing Muslim community through all kinds of event including sports, mentoring, community service game nights etc.

MAM Board continues to pursue the organization’s main objective of establishing a place of worship. The 4269 Regional Road property acquired for this purpose is currently undergoing reconstruction.


Updated: Jan 03, 2020

Milestones Achieved 

√ 12 Acres paid off property

√ Zoning approved as a place of worship

√ Site plan approved for outside civil work dated July 31

√ Hired contractor for outside civil work dated Sep 05

√ Construction of outside civil work started Sep 21

√ Septic tank has been completed Nov 15, 2019

√ Landscaping work completed Nov 20, 2019

√ Fire storage work will start Jan 15, 2010

√ 90% of Outside civil work has been completed – Updated Dec 27, 2019

√ The expected date for completion of outside civil work is Feb 30, 2020.

Project pictures

HICC Construction Pictures


Project Status

The construction work is broken down into three phases.

Phase 1  

Site Plan Approval

Completed

  • Prepare Site for construction     
  • Slit Fencing
  • Tree hoarding
  • Left Turn Signal
  • Letter of credit
  • Site Plan agreement
  • Revised Grading Plan
    … approximate $335,150
Phase 2         

Civil Work

90% Completed

  • Fire Tanks – In-Progress
  • Septic Tank – Completed
  • Parking Lot and Gravel driveway, site walk – 90% done
  • Landscaping, etc -Completed
    .… approximate $614,020

Pictures of Phase 2

http://miltonmasjid.com/hicc-construction-pictures

Phase 3         

Building Renovation and Construction

40% Completed

  • Fire safety additions
  • Reinforce floors – in-Progress
  • Mechanical, Electrical, Heating 
  • Prayer area, Bathroom, wudu area, Etc
    .… approximate $603,000

 


Project Phases and Cost Estimate


Proposed Floor Plan

√ Hired Architect 

√ Created a draft floor plan dated Jan 2019

√ Draft floor plan approved by BOD and members dated Feb 2019.

√ Architect attended meeting with city planner about the draft floor plan and received input from city planner dated Mar 2019

√ The architect created base drawing for pre-consultant meeting with  officials dated Mar 2019

√ Submitted revised site plan Application for parking, building extension Mar 15, 2019.

√ Expected Revised site plan approved – Apr, 2019

√ Permit drawing submission June, 2019

√  Demolition of the internal started July, 2019

√ Extension of front, Ramp and main entrance work started Oct, 2019

√ Beams work started Dec 2019

√ Framing in main prayer hall and Sister prayer area started Dec 2019

Project construction pictures

HICC Construction Pictures

HICC front elevation

 


Funding Targets

Project financial status
Revised Project cost

 $1.85 Million

Total Funds Raised (Incl. QH)  $1.5 Million
Available Funds  $400,000 
Funds Spent on project  $800,000 
Qard-e-Hasan  $25,000
Funds required  $400,000

Donate Now

To complete this project successfully and on time, we need your financial support and prayers, brothers and sisters. Please donate generously to have this place ready and open for us as soon as possible.

You can make a one time or recurring donation using the following methods

  • Credit Card, Paypal
  • Check
    • Please make the check out to the “Muslim Association of Milton”
    • You can mail the check to the address below, or drop it at the donation boxes at Juma, etc.
  • Direct Transfer
    • TD Canada Trust Bank
    • Transit # 3058, Account # 5000909

Location of the Project

HICC Address

4269 Regional Rd 25,

Oakville, ON L6M 4E9

“Whoever builds a mosque for Allah, then Allah will build for him a house like it in Paradise.”

Source: Ṣaḥīḥ al-Bukhārī 439, Ṣaḥīḥ Muslim 533