Masjid Project

Halton Islamic Community Center

(HICC)


Project Overview

We hope to use this facility as a hub to engage the Muslim community in Milton, Oakville and Burlington. We are especially excited about engaging the children of the growing Muslim community through all kinds of event including sports, mentoring, community service game nights etc.

MAM Board continues to pursue the organization’s main objective of establishing a place of worship. The 4269 Regional Road property acquired for this purpose is currently undergoing reconstruction.


Updated December 07, 2018

Milestones Achieved 

√ 12 Acres paid off property

√ Zoning approved as place of worship

√ Site plan approved for outside civil work dated July 31, 2018

√ Hired contractor for outside civil work dated Sep 05, 2018

√ Construction of outside civil work started Sep 21, 2018.

√ Septic tank and Fire storage work started in 4th week of Nov, 2018 and will finish Spring of 2019.

√ 70% of Civil work has been finished – Updated Nov 30.

√ Landscaping work started  4th week of Nov, 2018 and will finish May 31, 2019.

√ Expected date for completion of outside civil work is May 31st, 2019.


Project Status

The construction work is broken down into three phases.

Phase 1  

Site Plan Approval

Completed

  • Prepare Site for construction     
  • Slit Fencing
  • Tree hoarding
  • Left Turn Signal
  • Letter of credit
  • Site Plan agreement
  • Revised Grading Plan
    … approximate $335,150
Phase 2

Civil Work

70% Completed

  • Fire Tanks
  • Septic Tank
  • Parking Lot and Gravel driveway, site walk – 70% done
  • Landscaping, etc
    .… approximate $614,020

Pictures of Phase 2

http://miltonmasjid.com/hicc-construction-pictures

Phase 3

Building Renovation and Construction

In Progress 

  • Fire safety additions
  • Reinforce floors
  • Mechanical, Electrical, Heating
  • Prayer area, Bathroom, wudu area, Etc
    .… approximate $603,000

 


Project Phases and Cost Estimate


Proposed Floor Plan

√ Hired Architect dated Oct, 2017

√ Created draft floor plan dated Jan, 2018

√ Draft floor plan approved by BOD and members dated Feb, 2018.

√ Architect attended meeting with city planner about the draft floor plan and received input from city planner dated Mar, 2018

√ Architect created base drawing for pre consultant meeting with city, region and conservation officials dated August, 2018

√ Submitted revised site plan Application for parking, building extension Nov 15, 2019.

HICC front elevation

 


Funding Targets

Project financial status
Revised Project cost

 1.5 Million$

Total Funds Raised (Incl. QH) 1.32 Million
Available Funds 606 K
Funds Spent on project 726 K (include 230K Deposit)
Qard-e-Hasan 130 K
Funds required 298 K

Donate Now

To complete this project successfully and on time, we need your financial support and prayers brothers and sisters. Please donate generously to have this place ready and open for us as soon as possible.

You can make a one time or recurring donation using the following methods

  • Credit Card, Paypal
  • Check
    • Please make the check out to the “Muslim Association of Milton”
    • You can mail the check to the address below, or drop it at the donation boxes at Juma, etc.
  • Direct Transfer
    • TD Canada Trust Bank
    • Transit # 3058, Account # 5000909

Location of the Project

HICC Address

4269 Regional Rd 25,

Oakville, ON L6M 4E9

“Whoever builds a mosque for Allah, then Allah will build for him a house like it in Paradise.”

Source: Ṣaḥīḥ al-Bukhārī 439, Ṣaḥīḥ Muslim 533