Masjid Project

Halton Islamic Community Center

(HICC)


Project Overview

We hope to use this facility as a hub to engage the Muslim community in Milton, Oakville and Burlington. We are especially excited about engaging the children of the growing Muslim community through all kinds of event including sports, mentoring, community service game nights etc.

MAM Board continues to pursue the organization’s main objective of establishing a place of worship. The 4269 Regional Road property acquired for this purpose is currently undergoing reconstruction.


Milestones Achieved 

√ 12 Acres paid off property

√ Zoning approved as place of worship

√ Site plan approved for Civil work dated July 31, 2018

√ Hired contractor for Civil work dated Sep 05, 2018

√ Construction of Civil work started Sep 21, 2018.

√ Septic tank and Fire storage work will start either 3rd week of Nov, 2018 or Spring 2019 InShaa Allah.

√ 70% of Civil work has been finished – Updated Nov 10.

√ Landscaping work will start  2nd week of Nov, 2018 or spring 2019 InShaa Allah .

√ Expected date for completion of civil work is November 30, 2018.


Project Status

The construction work is broken down into three phases.

Phase 1  

Site Plan Approval

Completed

• Prepare Site for construction     
• Slit Fencing
• Tree hoarding
• Left Turn Signal
• Letter of credit
• Site Plan agreement
• Revised Grading Plan
… approximate $335,150Pictures of Phase 1http://miltonmasjid.com/hicc-construction-pictures
Phase 2

Civil Work

70% Completed

• Fire Tanks
• Septic Tank
• Parking Lot and Gravel driveway – 70% done as of Nov 10, 2018
• Landscaping, Etc
.… approximate $574,475
Phase 3

Building Renovation and Construction

In Progress 

• Fire safety additions
• Reinforce floors
• Mechanical, Electrical, Heating
• Prayer area, Bathroom, wudu area, Etc
.… approximate $603,000

 


Project Phases and Cost Estimate


Proposed Floor Plan

√ Hired Architect dated October, 2017

√ Created draft floor plan dated January, 2018

√ Draft floor plan approved by BOD and members dated February, 2018.

√ Architect attended meeting with city planner about the draft floor plan and received input from city planner dated March, 2018

√ Architect created base drawing for pre consultant meeting with city, region and conservation officials dated August, 2018

√ Meeting is hopefully schedule in next couple of week. Meeting request already sent dated August, 2018

HICC front elevation

 


Funding Targets

Project financial status
Project cost  1,300,000$
Total Funds Raised (Incl. QH)   1,160,000$
Available Funds  850,000$
Funds Spent on project  310,000$
Qard-e-Hasan  258,000$
Funds required  398,000$

Donate Now

To complete this project successfully and on time, we need your financial support and prayers brothers and sisters. Please donate generously to have this place ready and open for us as soon as possible.

You can make a one time or recurring donation using the following methods

  • Credit Card, Paypal
  • Check
    • Please make the check out to the “Muslim Association of Milton”
    • You can mail the check to the address below, or drop it at the donation boxes at Juma, etc.
  • Direct Transfer
    • TD Canada Trust Bank
    • Transit # 3058, Account # 5000909

Location of the Project

HICC Address

4269 Regional Rd 25,

Oakville, ON L6M 4E9