HICC Construction Pictures

HICC Phase 2- Civil Work

Last updated: Feb 21, 2020

  • Extension of building framing 
  • Weeping tiles installation work in basement 
  • Basement floor 

Last updated: Feb 02, 2020

January 2020

  • Frame work has been started in main hall and sisters area

Updated December 2019

  • Ramp and main entrance

Updated December 2019

  • Front Extension of Masjid
  • Concrete entrance from front 

Updated December 2019

  • Extra Porous Parking work started Nov 2019 and completed Dec 2019

Updated: Dec 07

  • Landscaping work

Updated: Nov 29

  • First layer of Asphalt

Updated: Oct 08


  • CONCRETE SIDEWALK AND PARKING LOT

Updated: Oct 27,


  • ROADWAY ENTRANCE PREP WORK
         PREPARE AREA TO BACK FILL ROADWAY ENTRANCE TO PARKING AS REQUIRED ON GRADING PLAN IN PART B
         COMPACT AREA AFTER BACKFILLING AS REQUIRED TO GET APPROVED COMPACTION TEST.
          SPREAD 150 MM OF GRANULAR A AND 250MM GRANUALR B
          COMPACT IN LAYERS USING HEAVY MACHINERY AND VIBRATORY ROLLERS

Updated: Oct 18


  • STARTED EXCAVATING PARKING AND DRIVEWAY
    • OUTLINE AND PREPARE TO EXCAVATE NEW DRIVEWAY AREA AND PARKING LOT
    • EXCAVATE AND DIG DOWN AREA OUTLINED AS PER GRADING PLAN

Updated: Oct 11


  • CULVERT PIPE INSTALLATION
    • EXCAVATED AREA AS REQUIRED TO INSTALL CULVERT PIPE
    • PREPARE AREA TO INSTALL CULVERT PIPE AS PER GRADING PLAN

Updated : Sep 29


  • First day of construction pictures

Updated : Sep 24


  • Site Permits received
  • Construction equipments in place

Updated : Sep 22


  • Mud Mat
  • Straw bale flow check dams
  • Riverstone check dams

Last updated : July 2019