HICC Construction Pictures

HICC Phase 2- Civil Work

  • First layer of Asphalt

Updated: Oct 08, 2018


  • CONCRETE SIDEWALK AND PARKING LOT

Updated: Oct 27, 2018


  • ROADWAY ENTRANCE PREP WORK
         PREPARE AREA TO BACK FILL ROADWAY ENTRANCE TO PARKING AS REQUIRED ON GRADING PLAN IN PART B
         COMPACT AREA AFTER BACKFILLING AS REQUIRED TO GET APPROVED COMPACTION TEST.
          SPREAD 150 MM OF GRANULAR A AND 250MM GRANUALR B
          COMPACT IN LAYERS USING HEAVY MACHINERY AND VIBRATORY ROLLERS

Updated: Oct 18, 2018


  • STARTED EXCAVATING PARKING AND DRIVEWAY
    • OUTLINE AND PREPARE TO EXCAVATE NEW DRIVEWAY AREA AND PARKING LOT
    • EXCAVATE AND DIG DOWN AREA OUTLINED AS PER GRADING PLAN

Updated: Oct 11, 2018


  • CULVERT PIPE INSTALLATION
    • EXCAVATED AREA AS REQUIRED TO INSTALL CULVERT PIPE
    • PREPARE AREA TO INSTALL CULVERT PIPE AS PER GRADING PLAN

Updated : Sep 29, 2018


  • First day of construction pictures

Updated : Sep 24, 2018


  • Site Permits received
  • Construction equipments in place

Updated : Sep 22, 2018


  • Mud Mat
  • Straw bale flow check dams
  • Riverstone check dams

Last updated : July, 2018