HICC Phase 2- Civil Work
Last updated: Dec 2020
– Electrical, HVAC, Fire Alarm, Plumbing inspection passed
Last updated: Oct 2020
-Sprinkle installed by volunteers
-SOD installed by volunteers
Last updated: July 15, 2020
-fire fighting tank Installation
Last updated: Feb 21, 2020
- Extension of building framing
- Weeping tiles installation work in the basement
- Basement floor
Last updated: Feb 02, 2020
January 2020
- Frame work has been started in main hall and sisters area
Updated December 2019
- Ramp and main entrance
Updated December 2019
- Front Extension of Masjid
- Concrete entrance from front
Updated December 2019
- Extra Porous Parking work started Nov 2019 and completed Dec 2019
Updated: Dec 07
- Landscaping work
Updated: Nov 29
- First layer of Asphalt
Updated: Oct 08
- CONCRETE SIDEWALK AND PARKING LOT
Updated: Oct 27,
- ROADWAY ENTRANCE PREP WORK
PREPARE AREA TO BACK FILL ROADWAY ENTRANCE TO PARKING AS REQUIRED ON GRADING PLAN IN PART B
COMPACT AREA AFTER BACKFILLING AS REQUIRED TO GET APPROVED COMPACTION TEST.
SPREAD 150 MM OF GRANULAR A AND 250MM GRANUALR B
COMPACT IN LAYERS USING HEAVY MACHINERY AND VIBRATORY ROLLERS
Updated: Oct 18
- STARTED EXCAVATING PARKING AND DRIVEWAY
- OUTLINE AND PREPARE TO EXCAVATE NEW DRIVEWAY AREA AND PARKING LOT
- EXCAVATE AND DIG DOWN AREA OUTLINED AS PER GRADING PLAN
Updated: Oct 11
- CULVERT PIPE INSTALLATION
- EXCAVATED AREA AS REQUIRED TO INSTALL CULVERT PIPE
- PREPARE AREA TO INSTALL CULVERT PIPE AS PER GRADING PLAN
Updated : Sep 29
- First day of construction pictures
Updated : Sep 24
- Site Permits received
- Construction equipments in place
Updated : Sep 22
- Mud Mat
- Straw bale flow check dams
- Riverstone check dams
Last updated : July 2019