HICC Construction Updates
Milestones Achieved
Phase 2- Out Side Civil Work
√ 12 Acres paid off property
√ Zoning approved as a place of worship
√ Site plan approved for outside civil work dated July 31
√ A hired contractor for outside civil work dated Sep 05
√ Construction of outside civil work started Sep 21
√ Septic tank has been completed Nov 15, 2019
√ Landscaping work completed Nov 20, 2019
√ Fire storage work will start on Jan 15, 2010
√ 90% of Outside civil work has been completed – Updated Dec 27, 2019
√ The expected date for completion of outside civil work is Feb 30, 2020.
Phase 3 – Building Renovation
√ Hired Architect
√ Created a draft floor plan dated Jan 2019
√ Draft floor plan approved by BOD and members dated Feb 2019.
√ Architect attended meeting with city planner about the draft floor plan and received input from city planner dated Mar 2019
√ The architect created a base drawing for the pre-consultant meeting with officials dated Mar 2019
√ Submitted revised site plan Application for parking, building extension Mar 15, 2019.
√ Expected Revised site plan approved – Apr 2019
√ Permit drawing submission June 2019
√ Demolition of the internal started July 2019
√ Extension of the front, Ramp, and main entrance work started Oct 2019
√ Beams work started Dec 2019
√ Framing in main prayer hall and Sister prayer area started Dec 2019
√ Beams work is going on on the ground floor and in the basement Feb 2020
√ Plumbing of wudu and washroom in ground floor and basement has been completed – June 2020
√ Sound system, CCTV and A/V wiring has been completed – July 2020
√ HVAC work has been completed – August 2020
√ Electrical and fire alarm wiring completed – Sep 2020
√ Contractor is working on fire separation framing issue – Oct 2020
√ Inspection of electrical, mechanical, plumbing and fire safety has been passed – Dec 02
√ Insulation work will start Dec 10, 2020