HICC Construction updates

HICC Construction Updates

 

Milestones Achieved

Phase 2- Out Side Civil Work

  • √ 12 Acres paid off property
  • √ Zoning approved as place of worship
  • √ Site plan approved for outside civil work dated July 31, 2018
  • √ Hired contractor for outside civil work dated Sep 05, 2018
  • √ Construction of outside civil work started Sep 21, 2018.
  • √ Septic tank and Fire storage work started in the 4th week of Nov 2018 and will finish Spring of 2019.
  • √ 70% of Civil work has been finished – updated Nov 30.
  • √ Landscaping work started  4th week of Nov 2018 and will finish May 31, 2019.
  • √ The expected date for completion of outside civil work is Jun 31st, 2019.

Phase 3 – Building Renovation

  • Hired Architect dated Oct 2017
  • √ Created a draft floor plan dated Jan 2018
  • √ Draft floor plan approved by BOD and members dated Feb 2018.
  • √ Architect attended meeting with city planner about the draft floor plan and received input from city planner dated Mar 2018
  • √ The architect created base drawing for pre consultant meeting with city, region and conservation officials dated Aug 2018
  • √ Submitted revised site plan Application for parking, building extension Nov 15, 2019.
  • √ Submitted building permit drawing Apr 9, 2019
  • √ Demolition of the internal wall will start the 1st week of May. 2019