HICC Construction updates

HICC Construction Updates

 

Milestones Achieved

Phase 2- Out Side Civil Work

√ 12 Acres paid off property

√ Zoning approved as a place of worship

√ Site plan approved for outside civil work dated July 31

√ Hired contractor for outside civil work dated Sep 05

√ Construction of outside civil work started Sep 21

√ Septic tank has been completed Nov 15, 2019

√ Landscaping work completed Nov 20, 2019

√ Fire storage work will start Jan 15, 2010

√ 90% of Outside civil work has been completed – Updated Dec 27, 2019

√ The expected date for completion of outside civil work is Feb 30, 2020.

Phase 3 – Building Renovation

√ Hired Architect 

√ Created a draft floor plan dated Jan 2019

√ Draft floor plan approved by BOD and members dated Feb 2019.

√ Architect attended meeting with city planner about the draft floor plan and received input from city planner dated Mar 2019

√ The architect created base drawing for pre-consultant meeting with  officials dated Mar 2019

√ Submitted revised site plan Application for parking, building extension Mar 15, 2019.

√ Expected Revised site plan approved – Apr, 2019

√ Permit drawing submission June, 2019

√  Demolition of the internal started July, 2019

√ Extension of front, Ramp and main entrance work started Oct, 2019

√ Beams work started Dec 2019

√ Framing in main prayer hall and Sister prayer area started Dec 2019

√ Beams work is going on in ground floor and in basement Feb 2020