Masjid Project

Halton Islamic Community Center (HICC)

We hope to use this facility as a hub to engage the Muslim Community in Milton, Oakville and Burlington. We are especially excited about engaging the children of the growing Muslim community through all kinds of event including sports, mentoring, community service game nights etc.

MAM Board continues to pursue the organization’s main objective of establishing a place of worship. The 4269 Regional Road property acquired for this purpose is currently undergoing reconstruction.

Milestones Achieved

  • 12 Acres paid off property
  • Zoning approved as a place of worship
  • Site plan approved for outside civil work dated July 31
  • A hired contractor for outside civil work dated Sep 05
  • Construction of outside civil work started Sep 21
  • Septic tank has been completed Nov 15, 2019
  • Landscaping work completed Nov 20, 2019
  • Fire storage work will start on Jan 15, 2010
  • The water storage tank has been installed – Sep 2020
  • 95% of Outside civil work has been completed – Updated Dec 02, 2020

Project Status

The construction work is broken down into three phases.

Phase 1: Site Plan Approval

  • Prepare Site for Construction
  • Slit Fencing
  • Tree hoarding
  • Left Turn Signal
  • Letter of credit
  • Site Plan agreement
  • Revised Grading Plan

Approximate $335,150

Phase 3: Building Renovation and Construction

  • Fire safety additions
  • Reinforce floors - in Progress
  • Mechanical, Electrical, Heating
  • Prayer area, Bathroom, wudu area, Etc

Approximate $1,000,830

Phase 2: Civil Work

  • Fire Tanks - Completed
  • Septic Tank - Completed
  • Parking Lot and Gravel driveway, site walk
  • Landscaping, etc - Completed

Approximate $814,020

Phase 1: Site Plan Approval

  • Prepare Site for Construction
  • Slit Fencing
  • Tree hoarding
  • Left Turn Signal
  • Letter of credit
  • Site Plan agreement
  • Revised Grading Plan

Approximate $335,150

Phase 2: Civil Work

  • Fire Tanks - Completed
  • Septic Tank - Completed
  • Parking Lot and Gravel driveway, site walk
  • Landscaping, etc - Completed

Approximate $814,020

Phase 3: Building Renovation and Construction

  • Fire safety additions
  • Reinforce floors - in Progress
  • Mechanical, Electrical, Heating
  • Prayer area, Bathroom, wudu area, Etc

Approximate $1,000,830

Proposed Floor Plan

  • Hired Architect
  • Created a draft floor plan dated Jan 2019
  • Draft floor plan approved by BOD and members dated Feb 2019.
  • Architect attended meeting with city planner about the draft floor plan and received input from city planner dated Mar 2019
  • The architect created a base drawing for the pre-consultant meeting with officials dated Mar 2019
  • Submitted revised site plan Application for parking, building extension Mar 15, 2019.
  • Expected Revised site plan approved – Apr 2019
  • Permit drawing submission June 2019
  • Demolition of the internal started July 2019
  • Extension of the front, Ramp, and main entrance work started Oct 2019
  • Beams work started Dec 2019
  • Framing in main prayer hall and Sister prayer area started Dec 2019
  • Beams work has been completed Feb 02, 2020
  • Plumbing of wudu and washroom in ground floor and basement has been completed – June 2020
  • Sound system, CCTV, and A/V wiring has been completed – July 2020
  • HVAC work has been completed – August 2020
  • Electrical and fire alarm wiring completed – Sep 2020
  • The contractor is working on the fire separation framing issue – Oct 2020
  • Inspection of electrical, mechanical, plumbing, and fire safety has been passed – Dec 02
  • Insulation work will start on Dec 10, 2020
  • Drywall in the main floor and basements has been installed Jan 2021
  • Compounding and sanding work has been finished in Feb 2021
  • Tiles in the main floor and basement washrooms and wadu area have been started in March 2021
  • RTU units ( Heating and cooling system) has been installed in March 2021
  • Millwork in the main hall has been completed April 2021
  • Pot lights have been installed in April 2021

Funding Targets

Project financial status
Revised Project cost

 $2.15 Million

Total Funds Raised (Incl. QH)  $1.8 Million
Available Funds  $300,000
Funds Spent on project  $1.5 Million
Funds required  $350,000